CPWD plinth area rates are the Central Public Works Department's standard costs per square metre for different types of buildings, at a base date. The cost index adjusts them for a city and a later date. Together they give a government benchmark for construction cost.
The 2025 rates
The current Plinth Area Rates have a base date of 1 April 2025, with Delhi as the base (index 100). For an RCC-framed residential building up to six storeys, the rate is ₹24,410 per sq m. Internal water supply and sanitary work add 9% and internal electrical work adds 12.5%, giving about ₹29,658 per sq m including GST.
The cost index
CPWD regional offices publish cost indices for cities in their region, usually twice a year. An index of 113 means building costs 13% more than in Delhi at the base date.
How to use them
- Take the plinth area rate for the building type, with the service additions.
- Multiply by the city's cost index and divide by 100.
- Multiply by the built-up area.
See the worked benchmarks for Delhi, Hyderabad, Chennai and Kolkata, or use the construction cost calculator.
Limits
The rates are for government works at CPWD specifications. They exclude land, lifts, external services and site development. Private quotes depend on the specification, so use the benchmark as a check, not as a quotation.