What is a cost-to-complete report?

How lenders and investors check how much money a part-built project still needs, and what the report covers.

A cost-to-complete report estimates how much more money and time a part-built project needs to finish, based on a site inspection and a review of the work done, the contracts and the costs already paid. Lenders use it before releasing more funds, taking over a stalled project or restructuring a loan.

What it covers

  • Work done: physical progress measured on site, item by item, against the approved drawings.
  • Money spent: costs incurred and paid, checked against bills and measurement records.
  • Work remaining: quantities still to be built and current rates for them.
  • Committed costs: contracts and orders already placed but not yet paid.
  • Escalation and contingency: price rises and a margin for unknowns.
  • Time: a realistic schedule to completion.

When it is needed

  1. Before each disbursement on a construction loan, as part of a Lender's Independent Engineer's work.
  2. When a project is delayed or over budget and lenders consider more funding.
  3. For stalled real estate projects, in insolvency or revival proposals.
  4. When an investor or new developer is taking over a project.

What the borrower should provide

Approved drawings, the original budget, contracts and work orders, running bills, payment records and the current schedule.